Medellín's new metro route is underway
The Metro de la 80 is a light-rail line that Metro de Medellín is building along Avenida 80, through the west of the city, from Caribe in the north to Aguacatala in the south. The Metro's manager now expects system tests to start in 2029, while the project's own website still says passengers will ride it from 2028.
What the Metro de la 80 is
The line will be Line E of the Metro, shown in pink on the network map. It's a metro ligero, a light-rail line, and the Metro's manager is clear that it isn't a tram: the trains run on steel rails with power from an overhead catenary, like conventional trains. The Metro says the line will benefit about a million people, 38% of the city's population and, most directly, the residents of Comuna 7, Robledo, and Comuna 11, Laureles and Estadio.
When the Metro de la 80 opens
The date has slipped, and the official sources don't yet agree. The project website still says riders will use the line from 2028. The Metro's general manager, Tomás Elejalde, said in August 2026 that system tests are planned to start in 2029, followed by trial runs with invited guests from the neighbourhoods along the line between 2029 and 2030. In November 2026 El Colombiano reported that the Alcaldía and the Metro estimate the line will enter operation in 2029. We haven't found a Metro or Alcaldía document that states 2029, so for now that date rests on the manager's words and the city's statements to the press.
The Metro de la 80 route from Caribe to Aguacatala
The line runs 13.25 km. It starts at Caribe station, follows Transversal 73 and then Calle 65 to the Facultad de Minas area, turns onto Avenida 80/81 and ends at Aguacatala. The whole trip will take 32 minutes, at up to 60 km/h.
Almost all of it runs at street level. The exceptions are a sunken section at San Germán and two viaducts, one at Caribe to cross Carrera 65 and the Autopista Norte, and one at Aguacatala to cross Calle 12 Sur. Avenida San Juan and Avenida Colombia get road interchanges so trains pass freely, and at crossings such as Calle 35, Avenida 33 and Calle 30 the trains will get priority at the traffic lights.
The 17 Metro de la 80 stops, from Caribe to Aguacatala
The line has 17 places to board: 14 street-level stops and 3 stations. The Metro hasn't published which barrios each stop serves, so we give a stop's location only where the Metro has published it.
| # | Stop | Type | Where it is | Connects with |
|---|---|---|---|---|
| 1 | Caribe | Station | Line A | |
| 2 | Córdoba | Stop | ||
| 3 | Ciudadela Educativa | Stop | ||
| 4 | San Germán | Station | ||
| 5 | Colombia | Stop | ||
| 6 | Floresta | Stop | Line B | |
| 7 | Los Pinos | Stop | ||
| 8 | San Juan | Stop | ||
| 9 | Villa de Aburrá | Stop | ||
| 10 | La Palma | Stop | Bus Line 1 | |
| 11 | San Bernardo | Stop | ||
| 12 | Loma de Los Bernal | Stop | ||
| 13 | La Mota | Stop | ||
| 14 | Cristo Rey | Stop | ||
| 15 | Guayabal | Stop | ||
| 16 | Apolo | Stop | ||
| 17 | Aguacatala | Station | At the existing Line A station | Line A |
How Metro de la 80 stops differ from its three stations
The 14 stops are light structures at street level, built for quick boarding close to homes and universities. The three stations, Caribe, San Germán and Aguacatala, are heavier buildings meant to carry bigger crowds and link the line with buses and bike lanes as well as other Metro lines. The Metro says the design includes lifts, ramps and step-free routes for people with reduced mobility.
Where the Metro de la 80 connects with Lines A and B and bus Line 1
Four points link the new line to the rest of the network: Line A at Caribe and Aguacatala, Line B at Floresta, and bus Line 1 at La Palma. Floresta matters most for people in Laureles and Estadio. The existing Line B station there is being enlarged and redesigned as the main transfer between Lines B and E, with lifts and new public space.
San Germán, Colombia's first underground rail station
San Germán will be the first underground station of any rail system in Colombia, set in a sunken section of about 500 metres that holds the tracks and the station building. Putting it underground keeps the trains out of the busy Avenida 80 and Calle 65 junction. Work on it started in June 2026.
The Metro de la 80 trains and how often they will run
The line will run 22 three-car trains, 20 in service and 2 in reserve. CRRC builds them in China and they're assembled in Bello. Each carries about 246 passengers, close to 600 when two are coupled, and they'll be air-conditioned, which the heavy Metro isn't. At peak times trains are planned up to three minutes apart, and the Metro sizes the line for 14,000 passengers an hour in each direction. The Metro's manager has been quoted putting expected use at about 250,000 passengers a day. Opening hours haven't been published.
Paying for a Metro de la 80 ride with the Cívica card
The line will share the Metro's fare system. The stations will have machines to buy and top up the Cívica card, and the Metro gives the example that you'll be able to ride from Caribe to the La Palma bus stop without paying an extra fare. The fare itself hasn't been announced.
How far the Metro de la 80 works have got
Works formally began on 28 April 2023. The headline progress figure needs reading carefully. On 11 November 2026 the mayor put the project at 55% of its overall schedule, but physical works at 9%. The 55% covers technical, administrative, financial and land work, so most of the building is still ahead. Land is the furthest along: on the same day the mayor said 97% of the more than 1,900 properties needed had been acquired.
Road closures on Avenida 80 during the works
Expect works along the corridor for years. The Iguaná bridge on Avenida 80, near Los Colores, was demolished from March 2026 with night closures and diversions, and the new bridge is due in the first quarter of 2027. Foundations for the Caribe viaduct run from the Avenida Regional by the Terminal del Norte to Transversal 78. Since 28 September 2026, Carrera 67 between Calle 71 and Transversal 78, and Calle 72 between Carreras 67 and 69, have been closed for good to build the depot in Pilarica and El Progreso, where the 22 trains will be kept and serviced.
Who is building the Metro de la 80 and what it costs
The civil works and the trains were contracted to Unión Temporal Metro de la 80, made up of CRRC (Hong Kong) and two Mota-Engil companies, with Ineo and Siemens Mobility as subcontractors. The Metro puts the cost at COP 3.5 trillion, 70% from the national government and 30% from Medellín.
National funding and the Metro de la 80 timeline
The national government is behind on its share. The mayor said in November 2026 that between COP 665,000 and 668,000 million for 2025 and 2026 is still pending, that the new national government has asked to reschedule its payments, and that a new calendar is being negotiated. Medellín says it has paid in more than COP 800,000 million on time and that no works have stopped, though the mayor added that a quick agreement matters to keep the bank loans behind the project flowing.
This guide covers Laureles specifically. The Laureles guide linked above has the best places there and what is on this week.
Events in Medellín in the next 2 weeks
- 8 AMRun clubThe Medellín Run Club | Brunch Party 🍳🪩
- 9 AMFitnessGlobull Social Run
- 8:30 PMConcertCandlelight: Coldplay vs. Ed Sheeran
- 7 AMGroup fitnessWellFest 2026
- 9 AMWellnessThe Sun Club
Written by Kole for Best Medellín, an English guide to wellness, food, hotels, things to do and events in Medellín.